Hardwick Ln. Road Closure

Road construction on Hardwick Ln. will be starting next Thursday 4/18/2019 running through Wednesday 5/1/2019.  This is obviously weather dependent and we will do our best to keep the shut down to a minimum knowing it is a hardship for a few people working and living along Hardwick Ln.  During this time we will construct the intersection of Hardwick and Baldrige and when it is complete traffic will be able to go north through Cartwright to Route H while we complete the rest of the Hardwick reconstruction.  We plan to have the entire newly constructed section of Hardwick tying into Route H complete by May 24.